boiler area set up questions
Last Post 23 Mar 2011 08:48 AM by BadgerBoilerMN. 3 Replies.
Printer Friendly
Sort:
PrevPrev NextNext
You are not authorized to post a reply.
Author Messages
BissetiUser is Offline
New Member
New Member
Send Private Message
Posts:38

--
23 Mar 2011 12:44 AM
Not exactly radiant, but I'm trying to set up a 9 zone system with a TT 175 boiler feeding 17 cast iron radiators (3 rad per zone).   This system is a central heating system for 5 apartments in north jersey.


I believe the boiler out piping is 1-1/2".  The lines are 3/4 pex.  I'm looking for advice on these questions:

Go with zone valves or pumps?

Is there a prebuilt maninfold set up that would work for me?

Is there any boiler area set up idea that would make the install simpler?  :()


And if anyone knows..is it best to feed old "American Radiator Company" rads from the top?


thanks much.
acwizardUser is Offline
Basic Member
Basic Member
Send Private Message
Posts:265

--
23 Mar 2011 01:49 AM
The first question that I have is what is the heating design load required from each zone and each radiator. This will then determine water temperature and flow rate. What is a TT boiler.
BissetiUser is Offline
New Member
New Member
Send Private Message
Posts:38

--
23 Mar 2011 08:26 AM
apt 1 - 2 zones load 7500 each
apt 2 - 2 zones load 9000 each
apt 3 - 2 zones load 14000 each
apt 4 - 2 zones load 16000 each

The rads I have are between 10 and 18 columns, 5 sections, 24" high cast iron.  A ten column has an puts out about 2750 btu an hour at 150 degrees.  two rads each zone.

The TT 175 is a triangle tube solo 175 boiler.

I'm running a 60 gallon heat transfer products indirect off the boiler.

BadgerBoilerMNUser is Offline
Veteran Member
Veteran Member
Send Private Message
Posts:2010

--
23 Mar 2011 08:48 AM
On old cast iron boiler conversions, I start with a heat load analysis, followed by sizing the radiation. Zone valves are more efficient in most gravity boiler conversions but flow control has to be attended to and primary/secondary is rarely needed if you do the math and the condensing boiler manufacturer allows it.

http://www.badgerboilerservice.com/boilerchoice.html
MA<br>www.badgerboilerservice.com
You are not authorized to post a reply.

Active Forums 4.1
Membership Membership: Latest New User Latest: croccohvacusa New Today New Today: 0 New Yesterday New Yesterday: 0 User Count Overall: 35027
People Online People Online: Visitors Visitors: 188 Members Members: 0 Total Total: 188
Copyright 2011 by BuildCentral, Inc.   Terms Of Use  Privacy Statement