bbicfUser is Offline
Registered Users
New Member
New Member
Send a message
Posts:26


07/11/2008 1:13 AM  
Have used fast foot and but is expensive, and have heard of people using tyvek, is this a suitable replacement for fast foot, does it hold up to the concrete as well, and does it have the same effect as fast foot. basically is it usable instead of fast foot.
Thanks
N
Chris JohnsonUser is Offline
Registered Users
Basic Member
Basic Member
Send a message
Posts:359


07/11/2008 2:37 AM  
It does the same thing plus Tyvek is much more readily available to me

Chris Johnson - Pro ICF
Napa, CA
Come for the wine, Stay for the ICF work
Paul StevensUser is Online
Registered Users
Basic Member
Basic Member
Send a message
Posts:149


07/11/2008 5:46 PM  
I have used Tyvec as well as Fast Foot. Tyvec is much cheaper, more available (can pick it up in most hardware stores) and does the same thing.
Paul Stevens
ICFconstructionUser is Offline
Registered Users
Basic Member
Basic Member
Send a message
Posts:173


07/11/2008 8:10 PM  
Good idea, I will have to give it a try. I bet it saves a lot of time.

ICFconstruction.net
Chris JohnsonUser is Offline
Registered Users
Basic Member
Basic Member
Send a message
Posts:359


07/11/2008 9:25 PM  
Saves a lot of money in concrete flowing out under the forms

Chris Johnson - Pro ICF
Napa, CA
Come for the wine, Stay for the ICF work
bbicfUser is Offline
Registered Users
New Member
New Member
Send a message
Posts:26


07/12/2008 1:38 AM  
so if you were doing an 8 or even 10 inch footins as I have to frequently do here, would you still use 2 x 4s and trust the tyvek to hold or 2x6s
Paul StevensUser is Online
Registered Users
Basic Member
Basic Member
Send a message
Posts:149


07/12/2008 6:51 AM  
yes, it will hold the concrete back on a 8 to 10 inch footing. I still prefer to use 2x8's when building footings that big but I do use the tyvec when I have a lot of steps involved, it is easier that cutting plywood to block in the sides, or when building on rock, Canadian shield, etc. it makes it lots quicker.
Paul Stevens
ICFconstructionUser is Offline
Registered Users
Basic Member
Basic Member
Send a message
Posts:173


08/01/2008 2:03 PM  
Does anyone do key-ways in your footings. If so how? I was thinking of putting a 2x4 on the underside of form spreaders.

ICFconstruction.net