ICF Gurus,
So I am doing my first owner build of our ICF house. My question is about my footings and incorporating them into the house/walls. I have ICF walls, with radiant floor heating, and the concrete floor will be my finished floor, I also have ICF deck roof. I'm thinking the correct order is
- Dig footings
- Prepare under slab (crushed stone compacted, plumbing electrical, vapor barrier)
- Rebar for footings, slab
- Install and brace two (?) courses of ICF block
- Tie in rebar from ICF into slab and footing rebar
- Foam insulation board and run radiant floor lines
- Mono-pour the footings with the slab and the first 2 courses of block
- Wait
- Finish stacking walls (add rebar with tie-ins from the first pour)
- Brace externally to avoid scarring floor
- Assemble deck, rebar tie into walls, brace from below (after protecting floor)
- Second mono-pour remaining portion of walls and roof deck
I know this gives me a cold joint in the wall but I don't really know how to avoid.
What's a better order?
TIA |