Myrtleboone,
"I'm a very visual person; does the inner vertical foam board travel along the inner footing wall all the way to the building surface, thus separating the footing from the slab? Anyway that you could sketch it for me and scan as a jpeg? That way I can describe it better to my foundation guy. It's assumed the wall is what you had described a couple days ago. (double 2x4 wall with 5 1/2" cavity). Thanks again."
The simple answer to you question is NO!
In explaining I'm going to assume you'll adopt the "flat topped" foundation wall.
The vertical foam is on the insides of the 'foundation walls" and extends ,vertically, from the top of footings under the foundation walls to the top of the foundation walls. The sub slab foam sits on the vertical foam as well as the foundation wall. The foundation walls are thick, let's say 18". Once the foundation walls and the vertical foam is in place the area inside the foam is prepared for the slab including,fill, drainage material and placing the sub slab foam which extends OVER the foundation wall. At least the foam over the foundation wall needs to be 100 PSI compressive strength. Temporary forms for the edges of the slab are constructed on top of the foundation walls, these forms sit on say 1/2" of the sub slab foam and are positioned so that the edge of the slab will be under the outer face of the inner stud wall's sheathing. Once the slab is cured the outer stud walls (taller) are framed (with pressure treated bottom plates) on the slab,temporary braces installed on their outer face and tilted into place on the foundation wall over the crush strips, temporarily braced and secured to the foundation wall, all without sheathing. Once the outer walls are up, the inner walls are framed, sheathed,treated with liquid vapor barrier, then tilted up sitting on the poly that is wrapped around the edge of the slab and a generous bead of acoustic sealant, the bottom plates are secured to slab, bracing installed etc. Since there is 5 1/2" of insulation between the stud walls and 3 1/2" in the studs of the outer wall and 3/4" of fiberboard and 1/4" of DC14 This puts about r36 around the edge of the slab for a lot less $ than using a 'stepped' foundation wall and 7" of vertical foam around the slab. Send an email to me at
[email protected] & I'll send you scans of sketches
Just for grins I repeated the whole wall r value calculation with r36 around the 4" slab under a 9 foot r51 wall, the whole wall r is reduced to r 50.5.
".Liebler-A couple more questions for you. How far away horizontally do you run the foam from the foundation perimeter? "
There is NO foam outside the foundation walls!